Karoon advances phased development plans for Brazil’s Neon oil field.

Karoon Energy has signed provisional agreements with Altera Infrastructure and TechnipFMC for a phased development of the Neon oil field in the Santos Basin offshore Brazil.

Late last year, Karoon decided to reassess its original plan, which had entered the FEED phase in April 2025. This was partly due to rising costs concerning the preferred FPSO.

New technical and commercial studies this year have focused on improving capital efficiency and reducing the downside risk of the development in Block S-M-1037.

The revised concept is a phased development designed to minimize upfront capex and address subsurface uncertainties. In the initial phase, Karoon now plans three subsea production wells (compared with four previously) and one gas injection well.

These would recover about 60 MMbbl.

Karoon has signed a memorandum of understanding with TechnipFMC to jointly mature the subsea technical scope, and it has entered an exclusive agreement with Altera for use of the 2007-built circular Sevan 300 FPSO Piranema Spirit.

Talks have taken place with potential construction yards on the required modifications and life extension scopes for the redeployment. The currently proposed nameplate capacity for the vessel would be in the range 25,000 to 30,000 bbl/d.

Karoon anticipates total development capex of $800 million to $950 million, but it will continue to assess further cost reductions via a leasing alternative, in parallel with farm-down discussions ahead of a possible FID in the second half of 2027.

Future development phases could take in resources from the Greater Neon area, covering the Piracucá and Goiá fields and the Neon West exploration prospect.

Source: offshore-mag.com