ExxonMobil Declares FID on Longtail Deepwater Gas Project Offshore Guyana

ExxonMobil has announced a final investment decision (FID) on its $12.5 billion Longtail gas and condensate project in ultradeep water on the Stabroek block offshore Guyana.

Expected to come onstream in 2030, Longtail is the eighth development undertaken by ExxonMobil affiliate ExxonMobil Guyana Ltd. (45% operating interest), together with partners: Chevron subsidiary Hess Guyana Exploration Ltd. (30%) and CNOOC Petroleum Guyana Ltd. (25%).

“Guyana is home to one of the world’s most prolific energy developments, and Longtail represents the next phase in realizing the full potential of its resources,” ExxonMobil Upstream Company President Dan Ammann said in a news release announcing FID on 12 November.

“By developing these gas and condensate resources, we’re unlocking new value for Guyana while delivering advantaged energy to meet growing global demand,” Ammann added.

Stabroek’s Pivot to Gas

Stabroek’s Liza Phase 1, Liza Phase 2, Payara, and Yellowtail projects are currently producing a combined 900,000 B/D of oil, according to ExxonMobil, which expects a fifth project, Uaru, to start up before the end of 2026, boosting production to more than 1 million B/D.

Projects No. 6 and 7, Whiptail and Hammerhead, aim to begin producing in 2027 and 2029, respectively, the company said.

Longtail, with its planned 45 subsea production and injection wells, is not about oil though. Instead, it targets nonassociated gas and condensate-rich reservoirs near to the Suriname maritime border and will use a floating production storage and offloading (FPSO) vessel designed to process 1.2 Bscf/D of gas and produce up to 250,000 B/D of condensate, according to ExxonMobil.

Guyana’s Ministry of Natural Resources said in a statement published by BNAmericas on 13 November that Longtail is projected to produce roughly 776 million bbl of condensate over a 30-year operating life from nine reservoirs, with development plans calling for 27 production wells and 18 gas injection wells.

In March, SBM Offshore announced it had won a front-end engineering and design (FEED) contract to build the FPSO, which will also store approximately 2 million bbl of condensate. To date, SBM Offshore has won six of eight FPSO awards. Longtail is structured as a phased contract that would advance from FEED to construction with the declaration of FID. Japan’s MODEC secured two contracts: Hammerhead and Uaru.

The government of Guyana is planning a second offshore gas pipeline to support onshore power generation, fertilizer production, mineral processing, and data centers, according to the news release. Currently, only one field-to-shore pipeline exists, transporting associated gas from the Liza Destiny and Liza Unity FPSOs.

Saipem Starts EPCI Ahead of FID
In April, Saipem was tapped by ExxonMobil Guyana Ltd. to receive a $150 million Limited Notice to Proceed (LNTP) on engineering, procurement, construction, and installation (EPCI) of subsea structures, umbilicals, risers and, flowlines on Longtail.

The LNTP enabled Saipem to begin preliminary detailed engineering and procurement activities at the project, in waters of about 1,750 m, while the main EPCI scope, including construction and installation, awaited FID.

In May, ExxonMobil applied to Guyana’s Environmental Protection Agency to authorize development of the Haimara offshore discovery, a potential ninthh project on the Stabroek block with yet another FPSO.

Source: jpt.spe.org