Yumna field first well reaches target depth
Masirah Oil has drilled the first well of its current Yumna field campaign offshore Oman to target depth and is moving to the second well, the operator said. The company said first production from the campaign has been delayed and that it will give updates as the project progresses.
Earlier slippage in the schedule
The campaign has slipped before. The company said in December 2025 that drilling would start in the first quarter of 2026, and in April it moved the start to May. Drilling began in October, as OAG reported on 22 October, with production from the new well then expected in November 2026.
Rig contract and funding for the campaign
Arabian Drilling signed a contract with Masirah Oil and Northern Offshore in August 2026 to drill two firm wells, plus two optional wells, in Oman. Jasmine Energy raised a $25 million (about AED 91.8 million) senior secured bond in December 2025, with proceeds to fund a three-well campaign at the field and general corporate purposes.
Yumna field history in Block 50
Masirah Oil is an indirect 87.5% subsidiary of Jasmine Energy, itself a subsidiary of Singapore-based Rex International. It operates Block 50 with a 100% interest. The block covers about 17,000 square kilometres in the Gulf of Masirah, east of Oman. Rex says on its website that about 9.6 million stock tank barrels of oil had been produced from the Yumna field by 31 December 2025.
First oil came in February 2020. Yumna-2 started producing in January 2021 and Yumna-3 in February 2021. In 2022 the floating storage tanker and the mobile offshore production unit were both replaced, so the tanker can stay in the field for several years without dry-docking. A multi-well programme finished in 2024, and its Yumna-5 well began production in April 2024.